| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| VII.001 | SUMINISTRO E INSTALACION DE ESTRUCTURA METALICA A BASE DE PLACAS DE DIFERENTES CALIBRES Y ESPESORES, ATORNILLADA EN LAS UNIONES, INCLUYE : MATERIALES, FABRICACION EN TALLER, ACARREOS Y FLETES, MANEJOS, MONTAJE, DESPERDICIOS, HERRAMIENTA, EQUIPO,TORNILLERIA ESPECIFICADA EN PLANOS,BISELES, CORTES, DOBLECES, HERRAMIENTA, EQUIPO,ENERGIA ELECTRICA, AJUSTES EN CAMPO, DETALLES EN CAMPO.( P.U.O.T.). | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| IPR DIF. MEDIDAS | IPR DIF. MEDIDAS | KG | 0.238700 | $9.90 | $2.36 |
| VIGA HP | VIGA HP | KG | 0.209900 | $9.90 | $2.08 |
| PLACA 1/4"@ 1" | PLACA 1/4"@ 1" | KG | 0.127800 | $9.90 | $1.27 |
| CANAL ESTRUCTURAL | CANAL ESTRUCTURAL | KG | 0.054250 | $6.00 | $0.33 |
| ANGULO DIF.MEDIDAS | ANGULO DIFERENTES MEDIDAS | kg | 0.054250 | $9.50 | $0.52 |
| GAS P/CORTES | GAS P/ CORTES | KG | 0.009000 | $3.96 | $0.04 |
| OXIGENO | OXIGENO | M3 | 0.008500 | $38.50 | $0.33 |
| SOLDADURA E7018 | SOLDADURA E 7018 | KG | 0.007330 | $18.00 | $0.13 |
| ALAMBRE TUBULAR | ALAMBRE TUBULAR | KG | 0.004000 | $30.00 | $0.12 |
| DISCO P/DESVASTE | DISCO P DESVASTE | PZA | 0.002200 | $31.25 | $0.07 |
| SPOT LABORATORIO | SPOT LABORATORIO | KG | 1.000000 | $0.15 | $0.15 |
| TORNILLERIA | TORNILLERIA | KG | 0.020000 | $50.00 | $1.00 |
| FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.021350 | $0.00 | $0.00 |
| PRIMER ESTR DUCO | PRIMER ESTR DUCO | LT. | 0.009600 | $47.00 | $0.45 |
| THINER | THINER | LT | 0.076190 | $8.50 | $0.65 |
| Suma de Material | $9.48 | ||||
| Mano de Obra | |||||
| CUADRILLA N° 341 | 1 of.pailero + 1 ayudante E. | JOR | 0.003330 | $603.89 | $2.01 |
| CUADRILLA N° 342 | 1 of.soldador + 1 ayudante E. | JOR | 0.002500 | $603.89 | $1.51 |
| CUADRILLA N° 344 | 1 of.pintor + 2 ayudante A. | JOR | 0.001670 | $676.23 | $1.13 |
| Suma de Mano de Obra | $4.65 | ||||
| Equipo | |||||
| API-EQUIPO OXICORTE | EQUIPO DE CORTE OXIGENO-GAS | hora | 0.013880 | $6.18 | $0.09 |
| API-ESMERILADORA | ESMERILADORA | hora | 0.028440 | $2.38 | $0.07 |
| API-SOLDADORA | SOLDADORA MILLER MODELO S64 | hora | 0.018310 | $9.26 | $0.17 |
| API-GRUA | GRUA DE 20 TON | hora | 0.002300 | $239.98 | $0.55 |
| API-EQUIPO PINTURA | EQUIPO DE PINTURA IPSA | hora | 0.035290 | $2.80 | $0.10 |
| Suma de Equipo | $0.97 | ||||
| Costo Directo | $15.10 |