| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| VIII.007 | CHAROLAS DE ACERO INOXIDABLE CON MARCO DEL MISMO MATERIAL PARA RECIBIR PRODUCTOS QUIMICOS DE LAS POSIBLES DERRAMAS EN PISOS CON MEDIDAS T DETALLES SEGUN PLANOS, INCLUYE: MATERIALES, MANO DE OBRA, FABRICACION EN TALLER, INSTALACION,FLETES, ACARREOS, HERRAMIENTA Y EQUIPO.( P.U.O.T.). | PIEZA. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PINT-ANTICORR-DP-RP2 | PINTURA ANTICORROSIVA MARCA DUPONT RP-2 | LT | 0.220000 | $82.50 | $18.15 |
| PINTURA DE ESMALTE | PINTURA DE ESMALTE COMEX 100 | LT | 0.180000 | $56.64 | $10.20 |
| ACERO INOX | ACERO INOXIDABLE CON MARCO | M2 | 0.000000 | $89.00 | $0.00 |
| ENERGIA ELECTRICA | ENERGIA ELECTRICA | KW | 1.600000 | $0.85 | $1.36 |
| SOLDADURA 7018 | SOLDADURA 70/18 | KG | 0.200000 | $30.28 | $6.06 |
| OXIGENO | OXIGENO | M3 | 0.160000 | $38.50 | $6.16 |
| GAS P/CORTES | GAS P/ CORTES | KG | 0.240000 | $3.96 | $0.95 |
| DISCO P/DESVASTE | DISCO P DESVASTE | PZA | 0.032000 | $31.25 | $1.00 |
| Suma de Material | $43.87 | ||||
| Mano de Obra | |||||
| CUADRILLA 04 | CUADRILLA DE PAILERIA(1 OFICIAL PAILERO + 1 OFICIAL SOLDADOR + 2 AYUDANTES) | Jor. | 0.020000 | $1,217.60 | $24.35 |
| Suma de Mano de Obra | $24.35 | ||||
| Equipo | |||||
| API-MAQ-SOLDAR-EST | SOLDADORA MILLER DIMENSION MOD. 652 | hora | 0.320000 | $10.80 | $3.46 |
| API-EQUIPO OXICORTE | EQUIPO DE CORTE OXIGENO-GAS | hora | 0.160000 | $6.18 | $0.99 |
| API-ESMERILADORA | ESMERILADORA | hora | 0.160000 | $2.38 | $0.38 |
| Suma de Equipo | $4.83 | ||||
| Costo Directo | $73.05 |