| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| VAR-004 | # 4 (1/2") | Kg |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0085-01 | VARILLA FY=4200 KG/CM2 NO. 4 ( 1/2" ) | ton | 0.001090 | $10,500.00 | $11.45 |
| 0085-01 | VARILLA FY=4200 KG/CM2 NO. 4 ( 1/2" ) | ton | 0.001090 | $10,500.00 | $11.45 |
| 0085-01 | VARILLA FY=4200 KG/CM2 NO. 4 ( 1/2" ) | ton | 0.001090 | $10,500.00 | $11.45 |
| 0082-05 | ALAMBRE RECOCIDO NO. 16 | kg | 0.035000 | $16.00 | $0.56 |
| 0082-05 | ALAMBRE RECOCIDO NO. 16 | kg | 0.035000 | $16.00 | $0.56 |
| 0082-05 | ALAMBRE RECOCIDO NO. 16 | kg | 0.035000 | $16.00 | $0.56 |
| Suma de Material | $36.02 | ||||
| Mano de Obra | |||||
| 02-0620 | CUADRILLA No 62 ( 1 FIERRERO + 1 AYUDANTE DE FIERRERO ) | jor | 0.004300 | $1,210.13 | $5.20 |
| 02-0620 | CUADRILLA No 62 ( 1 FIERRERO + 1 AYUDANTE DE FIERRERO ) | jor | 0.004300 | $1,210.13 | $5.20 |
| 02-0620 | CUADRILLA No 62 ( 1 FIERRERO + 1 AYUDANTE DE FIERRERO ) | jor | 0.004300 | $1,210.13 | $5.20 |
| Suma de Mano de Obra | $15.61 | ||||
| Auxiliar | |||||
| SEP-CON001 | SEPARADOR DE CONCRETO PARA CALZAR ACERO DE REFUERZO. | pieza | 0.035000 | $2.13 | $0.07 |
| SEP-CON001 | SEPARADOR DE CONCRETO PARA CALZAR ACERO DE REFUERZO. | pieza | 0.035000 | $2.13 | $0.07 |
| SEP-CON001 | SEPARADOR DE CONCRETO PARA CALZAR ACERO DE REFUERZO. | pieza | 0.035000 | $2.13 | $0.07 |
| Suma de Auxiliar | $0.22 | ||||
| Costo Directo | $51.85 |