| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| VAR-008 | # 8 (1") | Kg |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0088-00 | VARILLA FY=4200 KG/CM2 NO. 8 ( 1" ) | ton | 0.001050 | $10,500.00 | $11.03 |
| 0088-00 | VARILLA FY=4200 KG/CM2 NO. 8 ( 1" ) | ton | 0.001050 | $10,500.00 | $11.03 |
| 0082-05 | ALAMBRE RECOCIDO NO. 16 | kg | 0.030000 | $16.00 | $0.48 |
| 0082-05 | ALAMBRE RECOCIDO NO. 16 | kg | 0.030000 | $16.00 | $0.48 |
| Suma de Material | $23.01 | ||||
| Mano de Obra | |||||
| 02-0620 | CUADRILLA No 62 ( 1 FIERRERO + 1 AYUDANTE DE FIERRERO ) | jor | 0.004300 | $1,210.13 | $5.20 |
| 02-0620 | CUADRILLA No 62 ( 1 FIERRERO + 1 AYUDANTE DE FIERRERO ) | jor | 0.004300 | $1,210.13 | $5.20 |
| Suma de Mano de Obra | $10.41 | ||||
| Auxiliar | |||||
| SEP-CON001 | SEPARADOR DE CONCRETO PARA CALZAR ACERO DE REFUERZO. | pieza | 0.025000 | $2.13 | $0.05 |
| SEP-CON001 | SEPARADOR DE CONCRETO PARA CALZAR ACERO DE REFUERZO. | pieza | 0.025000 | $2.13 | $0.05 |
| G115100-9510 | Soldadura en varilla corrugada del No. 8 y 10, junta a tope biselado a 45 grados utilizando soldadura con electrodos E-9018, incluye: el suministro de los materiales, precalentamiento de las varillas a soldar, placa de respaldo, mano de obra. | junta | 0.020964 | $141.95 | $2.98 |
| G115100-9510 | Soldadura en varilla corrugada del No. 8 y 10, junta a tope biselado a 45 grados utilizando soldadura con electrodos E-9018, incluye: el suministro de los materiales, precalentamiento de las varillas a soldar, placa de respaldo, mano de obra. | junta | 0.020964 | $141.95 | $2.98 |
| Suma de Auxiliar | $6.06 | ||||
| Costo Directo | $39.48 |