| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 147 | DEMOLICION PARCIAL DE MURO EXISTENTE DE PIEDRA HASTA DEJARLO DE 34.90 MTS SEGÚN PLANO, Y HECHURA DE DOS GUARNICIONES AL NICIO Y FINAL DE MURO A BASE DE CONCRETO DE 250 KG/CM2 Y ACERO DE REFUERZO DE 3/8" CADA 20 CMS CON DOBLE PARRILLA BOLEADOS DE MENOS A MAS DESDE 10 CMS HASTA ALTURA DE MURO CON UN DESARROLLO DE 0.80 MTS CON UN NIVEL DE DESPLANTE DE 40 CMS POR EL ANCHO DEL MURO TERMINADO EN PINTURA COLOR NEGRO Y AMARILLO TRAFICO, INCLUYE: HERRA., M.O., LIMPIEZA EN ÁREA DE TRABAJO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN | LOTE |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGREGADO-003 | AGUA ACARREO INTERNO | M3 | 0.150000 | $25.00 | $3.75 |
| CIMBRAPLAY 16 MM. | CIMBRAPLAY 16 MM | m2 | 1.250000 | $86.00 | $107.50 |
| DUELA | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 4.500000 | $7.50 | $33.75 |
| CLAVO | Kg | 0.250000 | $16.00 | $4.00 | |
| ACERO DIF. DIAM. | ACERO REF.VAR.DIAM. | kg | 22.000000 | $8.61 | $189.42 |
| ALAMBRE REC. | ALAMBRE RECOCIDO | KG | 0.850000 | $10.00 | $8.50 |
| DIESEL | DIESEL | LITRO | 0.850000 | $7.00 | $5.95 |
| CHAFLAN 1" | CHAFLAN 1" | ML | 2.200000 | $3.00 | $6.60 |
| PINTURA ESMALTE COME | PINTURA ESMALTE | LT | 1.000000 | $58.45 | $58.45 |
| THINER ALKIDAL | thiner Ia. | Lt | 0.200000 | $15.00 | $3.00 |
| ESTOPA | KG | 1.500000 | $30.00 | $45.00 | |
| Suma de Material | $465.92 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 02 | Cuadrilla No. 02 (2 peones). | Jor. | 2.000000 | $510.81 | $1,021.62 |
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 2.000000 | $683.37 | $1,366.74 |
| CUAD OC 62 | CUAD. 1 FIERRERO + 1 AYUDANTE DE FIERRERO | jor | 1.000000 | $608.14 | $608.14 |
| CUADRILLA 19 | Cuadrilla de pintores(1 OF. PINTOR + 2 AYUDANTES) | Jor. | 0.250000 | $832.27 | $208.07 |
| Suma de Mano de Obra | $3,204.57 | ||||
| Equipo | |||||
| VIBRADOR P/CONCRETO | VIBRADOR PARA CONCRETO MOTOR KOHLE, DE 4 H.P., CON OPERADOR. | HORA | 0.246750 | $51.32 | $12.66 |
| Suma de Equipo | $12.66 | ||||
| Auxiliar | |||||
| CONCRETO F-C=250 H/O | Concreto F'c=250 Kg/cm2 RN rev 10 cmAM 3/4" | M3 | 0.246750 | $932.93 | $230.20 |
| Suma de Auxiliar | $230.20 | ||||
| Costo Directo | $3,913.35 |