| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 350 | CIMBRA Y DESCIMBRA EN PAVIMENTOS, INCLUYE: SUMINISTRO DE MATERIALES, HERRAMIENTA Y MANO DE OBRA. | m² |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MAD006 | POLIN DE MADERA DE PINO DE 2a. DE 4" X 4". | PT | 2.500000 | $17.45 | $43.63 |
| MAD002 | CHAFLAN DE MADERA DE PINO DE SEGUNDA DE 1". | ML | 1.100000 | $6.18 | $6.80 |
| FER002 | CLAVO DE 2 1/2" A 3 1/2" MARCA HYLSA. | KG | 0.110000 | $25.97 | $2.86 |
| ALB001 | ALAMBRE RECOCIDO MARCA HYLSA No. 18 | KG | 0.080000 | $22.00 | $1.76 |
| COM02 | DIESEL SIN, MARCA PEMEX | LT | 0.250000 | $8.00 | $2.00 |
| Suma de Material | $57.04 | ||||
| Mano de Obra | |||||
| CUA04 | CUADRILLA DE CARPINTERO 2DA + AYUDANTE | JOR | 0.062500 | $909.91 | $56.87 |
| Suma de Mano de Obra | $56.87 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)MO | 0.025000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)MO | 0.025000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| EVA05 | SIERRA CIRCULAR BLACK & DECKER MODELO CS1000 | HR | 0.500000 | $0.77 | $0.39 |
| AME-37 | CAMION CAPACIDAD DE 3.5 TON., MARCA FORD, F-350, MODELO 2008. | HORA | 0.002000 | $196.10 | $0.39 |
| Suma de Equipo | $0.78 | ||||
| Costo Directo | $114.69 |