| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 346 | LIMPIEZA, TRAZO Y NIVELACIÓN DEL ÁREA INTERVENIDA (CONSIDERANDO LA LIGA CON EL BANCO DE NIVEL DE REFERENCIA) INCLUYE: EQUIPO, HERRAMIENTA Y MANO DE OBRA. | m² |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ALB008 | CALHIDRA EN SACO DE 25 KG MARCA APASCO | KG | 0.020000 | $1.35 | $0.03 |
| MAD001 | BARROTE DE PINO 2 "X 4" X 10' DE 2da. | PT | 0.030000 | $12.63 | $0.38 |
| MAD006 | POLIN DE MADERA DE PINO DE 2a. DE 4" X 4". | PT | 0.025000 | $17.45 | $0.44 |
| FER002 | CLAVO DE 2 1/2" A 3 1/2" MARCA HYLSA. | KG | 0.005000 | $25.97 | $0.13 |
| ALB013 | CARRETE DE HILO DE PLASTICO PARA TRAZO CALIBRE 10 | ROL | 0.002000 | $19.00 | $0.04 |
| ALB014 | PUENTE METALICO PARA SEÑALIZACION | PZA | 0.033333 | $46.35 | $1.54 |
| ALB002 | AGUA PUESTA EN SITIO | M3 | 0.050000 | $18.21 | $0.91 |
| LAB108 | MATERIAL DE BANCO CON PARTICULAS DE 76 MM, 35% DE PORCENTAJE DE FINOS, LÍMITE LÍQUIDO (LL) 40 % MAX, ÍNDICE PLÁSTICO (IP) 20 % MAX, EXPANSIÓN 4.5 % MAX | M3 | 0.110000 | $190.34 | $20.94 |
| Suma de Material | $24.40 | ||||
| Mano de Obra | |||||
| CUA16 | CUADRILLA TOPOGRAFO + 4 CADENEROS | JOR | 0.002778 | $2,651.09 | $7.36 |
| CUA18 | CUADRILLA DE AYUDANTES. | JOR | 0.006250 | $1,232.42 | $7.70 |
| Suma de Mano de Obra | $15.07 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)MO | 0.025000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)MO | 0.025000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| ETO01 | NIVEL AUTOMATICO MARCA SECO, MOD. DS-32, DESVIACION ESTANDAR DEL 1.0 mm, EN 1 KM. DE DOBLE NIVELACION. ANTEOJO CON AUMENTO DE 32X. CON CIRCULO HORIZONTAL A 360º. EN ESTUCHE DE TRANSPORTE, INCLUYE TRIPIE DE ALUMINIO | HR | 0.022222 | $0.78 | $0.02 |
| ETO02 | TEODOLITO ELECTRONICO MARCA SPECTRA PHYSICS MOD. DET-20/10 CON LECTURA ELECTRONICA DE ANGULOS A 10" (SEGUNDOS) SEGÚN DIN18723 EN AMBOS CIRCULOS, INCLUYE TRIPIE DE ALUMINIO DE TRABE RAPIDO | HR | 0.022222 | $2.40 | $0.05 |
| AME-37 | CAMION CAPACIDAD DE 3.5 TON., MARCA FORD, F-350, MODELO 2008. | HORA | 0.002000 | $196.10 | $0.39 |
| EMP91 | MOTONIVELADORA CATERPILLAR 130G MOTOR DIESEL 135 H.P., INCLUYE OPERADOR | HR | 0.050000 | $344.47 | $17.22 |
| EMP90 | VIBROCOMPACTADOR VAP7OL SERIE CS 553 MARCA CATERPILLAR. | HR | 0.050000 | $258.87 | $12.94 |
| AME-59 | CAMIÒN AUTOTANQUE PARA REGADO DE AGUA, MARCA DINA DE 10,000 LITROS DE CAPACIDAD | HORA | 0.025000 | $264.18 | $6.60 |
| AME-37 | CAMION CAPACIDAD DE 3.5 TON., MARCA FORD, F-350, MODELO 2008. | HORA | 0.002000 | $196.10 | $0.39 |
| Suma de Equipo | $37.63 | ||||
| Auxiliar | |||||
| PBA97 | SUMINISTRO DE PERSONAL Y EQUIPO PARA PRUEBA DE COMPACTACION AL 95% PROCTOR | JOR | 0.002500 | $3,664.94 | $9.16 |
| Suma de Auxiliar | $9.16 | ||||
| Costo Directo | $86.26 |