| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| OC04-005-010 | DE 15 X 20 CM DE SECCION, ARMADA CON CUATRO VARILLAS DEL No. 3 A.R. Y ESTRI BOS DEL No. 2 A CADA 25 CM CON CIMBRA COMÚN | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO-01 | VARILLA CORRUGADA DEL # 3 ( 1/2") AL # 1 1/2" | ton | 0.002450 | $12,010.00 | $29.42 |
| CIMBRAPLAY. | CIMBRAPLAY DE 16 MM | M2 | 0.100000 | $107.38 | $10.74 |
| CLAVO. | CLAVO CON CABEZA | kg | 0.050000 | $15.00 | $0.75 |
| MADERA DE PINO 2A. | MADERA DE PINO DE 2A. | PT | 2.300000 | $10.00 | $23.00 |
| DESMOLDANTE | DESMOLDANTE PARA CIMBRA | litro | 0.050000 | $24.00 | $1.20 |
| ALAMBRON. | ALAMBRON LISO DE 1/4" ( NO. 2 ) | KG | 0.660000 | $12.88 | $8.50 |
| ALAMBRE REC. | ALAMBRE RECOCIDO | kg | 0.061000 | $14.55 | $0.89 |
| Suma de Material | $74.50 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 02 | CUADRILLA ( 1 OF. ALBAÑIL+1 AYUDANTE) | Jor | 0.125000 | $606.17 | $75.77 |
| Suma de Mano de Obra | $75.77 | ||||
| Auxiliar | |||||
| AND006 | ANDAMIO DE ACERO TUBULAR DE 4.00M. DE ALTURA CON RUEDAS Y BASE DE TABLONES DE MADERA. | R/D | 0.050000 | $69.74 | $3.49 |
| CONCRETO 150 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 1 1/2" | M3 | 0.033000 | $1,029.36 | $33.97 |
| Suma de Auxiliar | $37.46 | ||||
| Costo Directo | $187.73 |