| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| OC09-176-014 | MUEBLE DE MADERA, M-3 DE DIMENSIONES 2.40 M X 0.80 M X 0.75 MTS CON MODULOS DE CAJONERAS CON CORREDERAS METALICAS. DE ACUERDO A CROQUIS ANEXO. BARNIZ POLYFORM A TRES MANOS , RESANE, LIJADO, DEJANDO LA SUPERFICIE LISTA . UMF 65 | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA DE CEDRO | madera de cedro | pt | 34.000000 | $19.00 | $646.00 |
| CARRETILLAS P/CAJON | RIEL CON CARRETILLA PARA CAJON | PZA | 2.000000 | $65.00 | $130.00 |
| CHAPA P/CAJON | CHAPA PARA CAJON | PZA | 2.000000 | $85.00 | $170.00 |
| LAMINADO PLASTICO | Laminado plastico ralph wilson | m2 | 8.880000 | $135.00 | $1,198.80 |
| TRIPLAY DE CEDRO 6MM | triplay de cedro de 6 mm de espesor | m2 | 8.880000 | $98.00 | $870.24 |
| CLAVO ALFILERILLO | clavo alfilerillo | kg | 0.300000 | $26.00 | $7.80 |
| RESISTOL 5000 | Resistol 5000 | lt | 1.000000 | $120.00 | $120.00 |
| RESISTOL 850 | resistol 850 | lt | 0.300000 | $89.00 | $26.70 |
| Suma de Material | $3,169.54 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | CUADRILLA ( 1 CARPINTERO DE BANCO + 1 AYUDANTE ) | JOR | 5.500000 | $969.41 | $5,331.76 |
| Suma de Mano de Obra | $5,331.76 | ||||
| Costo Directo | $8,501.30 |