| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| OC06-005-015 | PROTECCIONES A BASE DE ACERO ESTRUCTURAL (ÁNGULO, SOLERA,CUADRTADO Y REDONDO). ACABADO PRIMER ANTICORROSIVO Y PINTURA ESMALTE ALQUIDÁLICO DOS MANOS, EN COLOR INDICADO POR EL IMSSINCLUYE RANURADO, ANCLAJE A MURO CON MORTERO CEMENTOARENA 1:5, RESANE Y PINTURA SIMILAR A LA EXISTENTE | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PRIMARIO ANTICORROSI | primario anticorrosivo | lt | 0.005000 | $54.00 | $0.27 |
| ANGULO METALICO | ANGULO METALICO ESTRUCTURAL | KG | 0.550000 | $16.00 | $8.80 |
| SOLERA METALICA | SOLERA METALICA | KG | 0.550000 | $15.00 | $8.25 |
| PINTURA DE ESMALTE | pintura de esmalte | lt | 0.006000 | $69.00 | $0.41 |
| SOLDADURA-E6013 | SOLDAURA ELECTRICA 1/8-6013 | KG | 0.005000 | $56.00 | $0.28 |
| GAS | GAS PARA CORTE | KG | 0.006000 | $8.70 | $0.05 |
| OXIGENO | OXIGENO | M3 | 0.004000 | $52.00 | $0.21 |
| DISCO PARA DESBASTE | disco para desbaste de metal | pza | 0.003000 | $45.00 | $0.14 |
| Suma de Material | $18.41 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 07 | CUADRILLA ( 1 HERRERO + 1 AYUDANTE ) | Jor | 0.010000 | $707.57 | $7.08 |
| Suma de Mano de Obra | $7.08 | ||||
| Costo Directo | $25.48 |