| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 20 | BACHEO SUPERFICIAL AISLADO POR UNIDAD DE OBRA TERMINADA | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PINTURA VIN | PINTURA VINILICA | LT | 1.200000 | $7.00 | $8.40 |
| CONCRETO ASFALTICO | CONCRETO ASFALTICO CONVENCIONAL ELABORADO EN PLANTA EN CALIENTE, L.A.B. | M3 | 1.300000 | $780.00 | $1,014.00 |
| Suma de Material | $1,022.40 | ||||
| Equipo | |||||
| EQ MENOR 04 | CORTADORA DE DISCO 8 HP | hora | 0.333000 | $128.54 | $42.80 |
| EQ 02 | RETROEXCAVADORA CAT 416 C | hora | 0.080000 | $212.72 | $17.02 |
| EQ 15 | CAMION VOLTEO 7 M3 | hora | 0.250000 | $269.61 | $67.40 |
| EQ 05 | MOTOCONFORMADORA CAT 12-G | hora | 0.017290 | $571.94 | $9.89 |
| EQ 06 | VIBROCOMPACTADOR CS 583C | hora | 0.018700 | $394.33 | $7.37 |
| EQ 09 | COMPACTADOR DE NEUMATICOS DYNAPAC CP221 | hora | 0.023480 | $277.29 | $6.51 |
| Suma de Equipo | $151.00 | ||||
| Auxiliar | |||||
| CUAD 01 | CUADRILLA NO 1 (1 AYUDANTE) | jor | 0.050000 | $279.67 | $13.98 |
| RIEGO LIGA | RIEGO DE LIGA CON EMULSION DE ROMPIMIENTO RAPIDO | LT | 1.200000 | $5.10 | $6.12 |
| Suma de Auxiliar | $20.10 | ||||
| Costo Directo | $1,193.50 |