| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3.- | RELLENOS EN TERRAPLENES, P.U.O.T. | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TEPETATE | TEPETATE | M3 | 1.300000 | $65.00 | $84.50 |
| AGUA | AGUA | M3 | 0.150000 | $30.00 | $4.50 |
| MALLA CICLONICA | MALLA CICLONICA | m2 | 0.100000 | $55.00 | $5.50 |
| Suma de Material | $94.50 | ||||
| Mano de Obra | |||||
| 03 ALB+PEON | CUADRILLA OFIC ALB+PEON | jor | 0.030000 | $606.94 | $18.21 |
| Suma de Mano de Obra | $18.21 | ||||
| Equipo | |||||
| APISONADORA | APISONADORA ( BAILARINA ) | Hora | 0.100000 | $69.53 | $6.95 |
| CAM CIST | CAMION CISTERNA | HR | 0.020408 | $241.94 | $4.94 |
| MOTONICONFORMADORA | MOTOCONFORMADORA 120B . | Hora | 0.033333 | $368.49 | $12.28 |
| RODVIBRA | COMPACTADOR VIBRATORIO CATERPILLAR CS533 DE 145 HP, 1.13 TON Y 2.13 M. DE ANCHO | hora | 0.033333 | $290.33 | $9.68 |
| CAMION VOLTEO | CAMION DE VOLTEO FORD 6m3. | Hora | 0.100000 | $235.43 | $23.54 |
| Suma de Equipo | $57.39 | ||||
| Costo Directo | $170.10 |