| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 16.- | SUBBASE HIDRAULICA, COMPACTADA AL 95%, P.U.O.T. | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA | AGUA | M3 | 0.150000 | $30.00 | $4.50 |
| MAT SUB HID | SUBBASE HIDRAULICA | m3 | 1.300000 | $80.00 | $104.00 |
| ACARREO 1ER KM | TARIFA DE ACARREO 1er KM | m3 | 1.300000 | $7.00 | $9.10 |
| ACARREO KM SUBS | TARIFA DE ACARREO KM-SUB | M3/KM | 39.000000 | $3.50 | $136.50 |
| Suma de Material | $254.10 | ||||
| Equipo | |||||
| CAM CIST | CAMION CISTERNA | HR | 0.033333 | $241.94 | $8.06 |
| MOTONICONFORMADORA | MOTOCONFORMADORA 120B . | Hora | 0.033333 | $368.49 | $12.28 |
| RODVIBRA | COMPACTADOR VIBRATORIO CATERPILLAR CS533 DE 145 HP, 1.13 TON Y 2.13 M. DE ANCHO | hora | 0.033333 | $290.33 | $9.68 |
| Suma de Equipo | $30.03 | ||||
| Costo Directo | $284.13 |