| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| C-6 | PISO FIRME DE 10 CM DE CONCRETO ARMADO CON MALLA 6-6/6 F`C 150KG/CM2 PARA RECIBIR LOSETA | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MALLA ELECTROSOLDADA | MALLA 6-6/6 | m2 | 1.050000 | $16.56 | $17.39 |
| Suma de Material | $17.39 | ||||
| Mano de Obra | |||||
| 02-0420 | CUADRILLA No 42 ( 1 ALBAÑIL + 2 PEONES ) | JOR | 0.038088 | $1,100.44 | $41.91 |
| Suma de Mano de Obra | $41.91 | ||||
| Concepto | |||||
| 020403 | CONCRETO HECHO EN OBRA RESISTENCIA NORMAL VACIADO CON CARRETILLA Y BOTES F'C=150 KG/CM2 REVENIMIENTO DE 10 CM AGREGADO MAXIMO 3/4" EN CIMENTACION | M3 | 0.116030 | $1,077.75 | $125.05 |
| Suma de Concepto | $125.05 | ||||
| Costo Directo | $184.35 |