| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| C-8 | ESCALON DE CONCRETO MARTERINADO NARIZ BOLEADA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PVC 2" | TUBO DE PVC 2" SANITARIO | ML | 1.050000 | $7.05 | $7.40 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.190000 | $17.00 | $3.23 |
| 1900-10 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 0.650000 | $5.65 | $3.67 |
| 0082-00 | ALAMBRE RECOCIDO NO. 16 | KG | 0.205000 | $14.50 | $2.97 |
| Suma de Material | $17.28 | ||||
| Mano de Obra | |||||
| 02-0010 | CUADRILLA No 1 ( 1 PEON ) | JOR | 0.171497 | $315.65 | $54.13 |
| Suma de Mano de Obra | $54.13 | ||||
| Auxiliar | |||||
| 03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3¬ USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.111100 | $23.08 | $2.56 |
| 03-2040 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.027600 | $877.72 | $24.23 |
| Suma de Auxiliar | $26.79 | ||||
| Concepto | |||||
| ACERC3 * | Acero de refuerzo en cimentación del No. 3, de Fy=4200 kg/cm2, incluye: materiales, pruebas de resistencia de acuerdo con especificaciones, acarreos, cortes, desperdicios, habilitado, amarres, mano de obra, equipo y herramienta (P.U.O.T.). | TON | 0.004000 | $12,053.68 | $48.21 |
| Suma de Concepto | $48.21 | ||||
| Costo Directo | $146.41 |