| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| C-2 | CASTILLO DE CONCRETO HECHO EN OBRA .15X.15CM F`C 150KG/CM2 CON ARMEX | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 1.150000 | $5.65 | $6.50 |
| 1900-10 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 0.520000 | $5.65 | $2.94 |
| 1900-15 | MADERA DE PINO DE 3A. EN POLIN DE 4" X 4" | PT | 2.040000 | $9.30 | $18.97 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.135000 | $17.00 | $2.30 |
| 0950-05 | DIESEL | LT | 0.600000 | $5.95 | $3.57 |
| ARMEX 15 15 | ARMEX 15X15 | ML | 1.050000 | $20.24 | $21.25 |
| Suma de Material | $55.52 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.095456 | $784.75 | $74.91 |
| Suma de Mano de Obra | $74.91 | ||||
| Auxiliar | |||||
| 03-2040 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.023600 | $877.72 | $20.71 |
| 03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3¬ USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.160000 | $23.08 | $3.69 |
| Suma de Auxiliar | $24.41 | ||||
| Costo Directo | $154.84 |