| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| BARD-07 | CONSTRUCCION DE BARDA PERIMETRAL HECHA A BASE DE RODAPIE DE CONCRETO F'C=250 KG/CM2 DE SECCION DE 0.40 X 1.20 MTS ARMADO CON 12 Vs. DEL No 3 (3/8") Y ANILLOS DEL No 3 (3/8") A CADA 20 CMS.,FORO CON PIEDRA LAJA CON MORTERO CEMNETO ARENA 1:4, Y PERFIL PTR DE 4"X4" ( ROJO ) A CADA 15 CMS A CENTROS ANCLADOS AL RODAPIE PARA UNA ALTURA FINAL DE 2.50 MTS, INCLUYE PRIMARIO ANTICORROSIVO Y PINTURA DE ESMALTE COMO ACABADO FINAL. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CD-ACERO-PTR 4*4 | PERFIL PTR DE 4"X4" ( ROJO ) | kg | 221.670000 | $12.40 | $2,748.71 |
| CD-ACABA-PINT-03 | PRIMARIO ANTICORROSIVO | lts | 0.250000 | $80.00 | $20.00 |
| CD-PINTU-ESMALTE-02 | PINTURA DE ESMALTE ALKIDALICO | lts | 0.900000 | $100.00 | $90.00 |
| CD-CARP-BLA-12 | THINER DE PRIMERA | LTS | 0.600000 | $20.00 | $12.00 |
| CD-LAJA-01 | PIEDRA LAJA | M2 | 1.600000 | $110.00 | $176.00 |
| Suma de Material | $3,046.71 | ||||
| Mano de Obra | |||||
| CD-CUADRILLA 19 | Cuadrilla de fierreros. Incluye : fierrero, ayudante, cabo y herramienta. | Jor | 0.200000 | $671.14 | $134.23 |
| Suma de Mano de Obra | $134.23 | ||||
| Auxiliar | |||||
| MEZ0004 | Mortero cemento - arena gruesa 1 : 5 | m3 | 0.080000 | $885.32 | $70.83 |
| Suma de Auxiliar | $70.83 | ||||
| Concepto | |||||
| J-CIMEN-03 | CIMBRA EN CIMENTACION (CONTRATRABES, ZAPATS, DADOS) ACABADO COMUN, DE MADERA DE PINO, INCLUYE CIMBRADO Y DESCIMBRADO, LIMPIEZA. HERRAMIENTA, MANO DE OBRA. | M2 | 2.400000 | $161.41 | $387.38 |
| J-CIMEN-04 | ACERO DE REFUERZO DE CIMENTACION (ZAPATAS, CONTRATRABES, TRABES DE LIGA DADOS) 3/8" DE DIAMETRO DEL No. 3 GRADO 42 Fy=4200 KGS/CM2 INCLUYE SUMINISTRO, HABILITADO, COLOCACION, ARMADO, ALAMBRE RECOCIDO, TRAZO, CORTES, SILLETAS, DESPERDICIO, HERRAMIENTA, ACARREOS, FLETES Y LIMPIEZA. INCLUYE TRASLAPES, GANCHOS, ESCUADRAS. | TON | 0.014000 | $12,577.15 | $176.08 |
| J-CIMEN-10 | CONCRETO PREMEZCLADO EN CIMENTACION F'C=250 KGS/CM2 INCLUYE ADITIVO RESISTENCIA NORMAL REVENIMIENTO DE 14 MAS O MENOS 2.5 CM TMA 19 MM , BOMBEO, COLADO, VIBRADO Y DESPERDICIO, PRUEBAS DE LABORATORIO, MATERIAL Y MANO DE OBRA. | M3 | 0.480000 | $1,242.84 | $596.56 |
| Suma de Concepto | $1,160.03 | ||||
| Costo Directo | $4,411.79 |