| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| J-ESTR-EST-12 | CIMBRA APARENTE EN COLUMNAS DE CONCRETO DE CONCRETO HIDRAULICO INCLUYE DESCIMBRADO, MANO DE OBRA, EQUIPO Y HERRAMIENTA. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CD-CIMBRA-MADERA-08 | Triplay de 1.22x2.44m 16 mm 1c (pieza) | pza | 0.077800 | $420.00 | $32.68 |
| CD-CIMBRA-MADERA-01 | Barrote 1 1/2" x 4" x 8' | pt | 1.671900 | $13.83 | $23.12 |
| CD-CIMBRA-MADERA-07 | Duela 1" x4"x8 1/4' | pt | 1.187000 | $14.18 | $16.83 |
| CD-CIMBRA-MADERA-03 | Polin de 3 1/2"x3 1/2" regular | pt | 0.878500 | $19.58 | $17.20 |
| CD-CIMBRA-MADERA-05 | Chaflan de 3/4"x 3/4" x 8' | m | 0.730000 | $2.50 | $1.83 |
| CD-CIMBRA-MADERA-06 | Clavo c/cabeza de 2"-4" | kg | 0.072300 | $9.13 | $0.66 |
| CD-ACERO-ALAMBRE-09 | Alambre recocido Calibre 18 | kg | 0.240200 | $9.59 | $2.30 |
| COMBUSTIBLE- 01 | DIESEL | LT | 0.610000 | $7.24 | $4.42 |
| Suma de Material | $99.04 | ||||
| Mano de Obra | |||||
| CD-CUADRILLA 18 | Cuadrilla de carpinteros para cimbras. Incluye : carpintero, ayudante, cabo y herramienta. | Jor | 0.155000 | $671.14 | $104.03 |
| Suma de Mano de Obra | $104.03 | ||||
| Costo Directo | $203.06 |