| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1 | LIMPIEZA, DESMONTE, DESPALME, TRAZO Y NIVELACION DEL TERRENO. INCLUYE: HERRAMIENTA, MANO DE OBRA, MAQUINARIA Y EQUIPO, CARGA, TRANSPORTE Y DESCARGA DE LOS PRODUCTOS DE DESHECHO HASTA EL SITIO DE TIRO FUERA DE LA OBRA, (E-431-01-4-4005). | m² |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| B2 X 4 | BARROTE DE PINO 2 "X 4" X 10' DE 2da. | PT | 0.030000 | $9.98 | $0.30 |
| D1"X4" | DUELA DE MADERA DE PINO DE 2a. DE 1" X 6" | pt. | 0.046000 | $13.43 | $0.62 |
| POLIN 4"X4" PINO | POLIN DE MADERA DE PINO DE 3a. DE 4" X 4". | pt. | 0.025000 | $13.43 | $0.34 |
| C2 1/2-3 1/2" | CLAVO DE 2 1/2" A 3 1/2" MARCA HYLSA. | kg | 0.005000 | $9.59 | $0.05 |
| HILO | HILO PARA TRAZO | carrete | 0.002000 | $24.72 | $0.05 |
| CAL | CALHIDRA | ton | 0.001000 | $959.06 | $0.96 |
| Suma de Material | $2.31 | ||||
| Mano de Obra | |||||
| CUAD048 | CUADRILLA TOPOGRAFO + 4 CADENEROS | jor | 0.001540 | $1,631.30 | $2.51 |
| CUAD047 | CUADRILLA AYUDANTES GENERALES | jor | 0.020000 | $536.33 | $10.73 |
| Suma de Mano de Obra | $13.24 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MAQ406 | EQUIPO PARA TOPOGRAFIA | hora | 0.015400 | $42.68 | $0.66 |
| Suma de Equipo | $0.66 | ||||
| Costo Directo | $16.21 |