| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 811 | 3” (76 mm) DIÁM. NOMINAL, CÉD. 80 | METRO |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUB078 | TUBERÍA DE ACERO AL CARBON ASTM A-106 Gr. B, EXTREMOS BISELADOS, SIN COSTURA DE 3” (76 mm) DÍAM. NOMINAL, CEDULA 80 | MT | 1.000000 | $282.98 | $282.98 |
| MAT-CON004 | SOLDADURA NOM H-77 AWS E-6010, 7018 | KG | 0.425000 | $19.18 | $8.15 |
| MAT-CON001 | OXIGENO | M3 | 0.025000 | $37.41 | $0.94 |
| MAT-CON002 | ACETILENO | KG | 0.012500 | $133.34 | $1.67 |
| MAT-CON003 | DISCO ABRASIVO DE 1/4" | PZA | 0.150000 | $57.55 | $8.63 |
| Suma de Material | $302.37 | ||||
| Mano de Obra | |||||
| CUAD025 | CUADRILLA OPERARIO ESPECIALISTA SOLDADOR + TUBERO + AYUDANTES | jor | 0.055560 | $1,664.37 | $92.47 |
| Suma de Mano de Obra | $92.47 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MAQ031 | EQUIPO PARA SOLDURA Y CORTE | hora | 0.555600 | $62.95 | $34.98 |
| Suma de Equipo | $34.98 | ||||
| Costo Directo | $429.81 |