| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 93 | DE 40 CM DE ESPESOR, (D-431-01-4-4695) | m² |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.440000 | $1,568.24 | $690.03 |
| CONC. F-C=100KG/CM2. | CONCRETO HECHO EN OBRA F'C=100 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 | 0.055000 | $950.72 | $52.29 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.495000 | $134.17 | $66.41 |
| ACERO CIMEN. NO. 6 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 6 ( 3/4" ) DE DIAM. | TON | 0.024400 | $8,410.57 | $205.22 |
| EXCAVACION | EXCAVACION CON EQUIPO PESADO | M3 | 1.600000 | $36.03 | $57.65 |
| Suma de Auxiliar | $1,071.60 | ||||
| Costo Directo | $1,071.60 |