| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 84 | ZAPATAS DE 220 X 220 CM Y 20 CM DE ALTURA, CON DADO DE 35 X 35 CM (D-431-01-4-4450) | Pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 1.239700 | $1,568.24 | $1,944.15 |
| CONC. F-C=100KG/CM2. | CONCRETO HECHO EN OBRA F'C=100 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 | 0.290950 | $950.72 | $276.61 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 1.530650 | $134.17 | $205.37 |
| ACERO CIMEN. NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.035050 | $9,192.72 | $322.20 |
| ACERO CIMEN. NO. 4 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 4 ( 1/2" ) DE DIAM. | TON | 0.015840 | $8,944.41 | $141.68 |
| ACERO CIMEN. NO. 5 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 5 ( 5/8" ) DE DIAM. | TON | 0.075504 | $8,564.97 | $646.69 |
| CIMBRA COMUN CIMENTA | CIMBRA COMUN DE MADERA DE PINO DE 2da. | M2 | 3.938000 | $151.18 | $595.35 |
| EXCAVACION | EXCAVACION CON EQUIPO PESADO | M3 | 6.982800 | $36.03 | $251.59 |
| Suma de Auxiliar | $4,383.64 | ||||
| Costo Directo | $4,383.64 |