| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 127 | DE 30 CM DE ESPESOR, (D-431-01-4-4240,4245) | m² |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.330000 | $1,568.24 | $517.52 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.330000 | $134.17 | $44.28 |
| CIMBRA COMUN LOSAS | CIMBRA COMUN EN MUROS, COLUMNAS, TRABES Y LOSAS. | M2 | 2.050000 | $176.10 | $361.01 |
| ACERO ESTRUC. NO. 6 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA FY=4200 KG/CM2. DEL No. 6 ( 3/4" ) DE DIAM. | TON | 0.049500 | $8,554.49 | $423.45 |
| Suma de Auxiliar | $1,346.25 | ||||
| Costo Directo | $1,346.25 |