| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 151 | DE 15 X 40 CM, (D-431.01-4-4110, 4111) | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.066000 | $1,568.24 | $103.50 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.066000 | $134.17 | $8.86 |
| CIMBRA APARENTE TRAB | CIMBRA APARENTE EN MUROS, COLUMNAS, TRABES Y LOSAS. | M2 | 1.045000 | $215.94 | $225.66 |
| ACERO ESTRUC. NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.002464 | $9,398.41 | $23.16 |
| ACERO ESTRUC. NO. 6 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA FY=4200 KG/CM2. DEL No. 6 ( 3/4" ) DE DIAM. | TON | 0.015593 | $8,554.49 | $133.39 |
| Suma de Auxiliar | $494.56 | ||||
| Costo Directo | $494.56 |