| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 565 | 8” DIAM. (203 MM) BORE = 7.981” 150# R. F. | PIEZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CON-005A | ARENA SILICA MALLA 16/30 (TON) | TON | 0.004400 | $741.54 | $3.26 |
| PIN001 | PRIMARIO INORGANICO DE ZINC RP-4 TIPO "B" | LT | 0.010730 | $121.57 | $1.30 |
| PIN006 | SOLVENTE 50/50 | LT | 0.000540 | $8.14 | $0.00 |
| PIN012 | ACABADO RA-26 | LT | 0.036670 | $143.89 | $5.28 |
| PIN007 | SOLVENTE 80/20 | LT | 0.007330 | $11.29 | $0.08 |
| CON-006 | TRAPO DE ALGODON | KG | 0.001760 | $46.27 | $0.08 |
| MA-307 | THINNER | LT | 0.008800 | $11.96 | $0.11 |
| Suma de Material | $10.12 | ||||
| Mano de Obra | |||||
| CUAD017 | CUADRILLA SAND BLASTERO-PINTOR + AYUDANTE | jor | 0.005180 | $832.18 | $4.31 |
| Suma de Mano de Obra | $4.31 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MAQ012 | EQUIPO PARA SAND BLAST Y PINTURA | hora | 0.051800 | $141.60 | $7.33 |
| Suma de Equipo | $7.33 | ||||
| Costo Directo | $21.76 |