| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 528 | 3” DIAM. (76 MM) LIMPIEZA | METROS |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CON-005A | ARENA SILICA MALLA 16/30 (TON) | TON | 0.013960 | $741.54 | $10.35 |
| PIN001 | PRIMARIO INORGANICO DE ZINC RP-4 TIPO "B" | LT | 0.034060 | $121.57 | $4.14 |
| PIN012 | ACABADO RA-26 | LT | 0.116370 | $143.89 | $16.74 |
| PIN006 | SOLVENTE 50/50 | LT | 0.001700 | $8.14 | $0.01 |
| PIN007 | SOLVENTE 80/20 | LT | 0.023270 | $11.29 | $0.26 |
| CON-006 | TRAPO DE ALGODON | KG | 0.005590 | $46.27 | $0.26 |
| MA-307 | THINNER | LT | 0.027930 | $11.96 | $0.33 |
| Suma de Material | $32.11 | ||||
| Mano de Obra | |||||
| CUAD017 | CUADRILLA SAND BLASTERO-PINTOR + AYUDANTE | jor | 0.016430 | $832.18 | $13.67 |
| Suma de Mano de Obra | $13.67 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MAQ012 | EQUIPO PARA SAND BLAST Y PINTURA | hora | 0.164300 | $141.60 | $23.26 |
| Suma de Equipo | $23.26 | ||||
| Costo Directo | $69.04 |