| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 137 | DE 12 X 20 CM, (D-431-01-4-4725) | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.026400 | $1,568.24 | $41.40 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.026400 | $134.17 | $3.54 |
| CIMBRA COMUN LOSAS | CIMBRA COMUN EN MUROS, COLUMNAS, TRABES Y LOSAS. | M2 | 0.704000 | $176.10 | $123.97 |
| ACERO ESTRUC. NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.002464 | $9,398.41 | $23.16 |
| ACERO ESTRUC. NO. 2 | HABILITADO Y ARMADO DE ACERO DE REFUERZO F'Y = 2530 KG/CM2, DEL #2 (1/4") | TON | 0.000442 | $8,944.41 | $3.95 |
| Suma de Auxiliar | $196.03 | ||||
| Costo Directo | $196.03 |