| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 15 | REGISTRO DE 90 X 90 X 135 cm DE ALTURA MAX. (D-431-01-4-4045) | Pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| REJILLA NO.1321-RG | REJILLA No.1321-RG CON ARRESTADOR DE FLAMA | PZA | 1.000000 | $1,362.46 | $1,362.46 |
| Suma de Material | $1,362.46 | ||||
| Mano de Obra | |||||
| CUAD047 | CUADRILLA AYUDANTES GENERALES | jor | 0.567000 | $536.33 | $304.10 |
| Suma de Mano de Obra | $304.10 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| CONC. F-C=100KG/CM2. | CONCRETO HECHO EN OBRA F'C=100 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 | 0.044550 | $950.72 | $42.35 |
| CONC. F-C=200KG/CM2. | CONCRETO HECHO EN OBRA F'C=200 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.825000 | $1,453.67 | $1,199.28 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.869550 | $134.17 | $116.67 |
| TAPA REG-69X69 | TAPA Y CONTRAMARCO PARA REGISTRO DE 69 X 69 CMTS | PZA | 1.000000 | $503.33 | $503.33 |
| ACERO CIMEN. NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.068750 | $9,192.72 | $632.00 |
| CIMBRA COMUN CIMENTA | CIMBRA COMUN DE MADERA DE PINO DE 2da. | M2 | 3.240000 | $151.18 | $489.82 |
| EXCAVACION | EXCAVACION CON EQUIPO PESADO | M3 | 1.093500 | $36.03 | $39.40 |
| Suma de Auxiliar | $3,022.85 | ||||
| Costo Directo | $4,689.41 |