| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 163 | DE 20 X 40 CM, (D-431.01-4-4720, 4610) | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.880000 | $1,568.24 | $1,380.05 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.880000 | $134.17 | $118.07 |
| CIMBRA APARENTE TRAB | CIMBRA APARENTE EN MUROS, COLUMNAS, TRABES Y LOSAS. | M2 | 1.100000 | $215.94 | $237.53 |
| ACERO ESTRUC. NO. 2 | HABILITADO Y ARMADO DE ACERO DE REFUERZO F'Y = 2530 KG/CM2, DEL #2 (1/4") | TON | 0.002761 | $8,944.41 | $24.70 |
| ACERO ESTRUC. NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.001232 | $9,398.41 | $11.58 |
| ACERO ESTRUC. NO. 4 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA FY=4200 KG/CM2. DEL No. 4 ( 1/2" ) DE DIAM. | TON | 0.004400 | $9,131.61 | $40.18 |
| Suma de Auxiliar | $1,812.11 | ||||
| Costo Directo | $1,812.11 |