| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 106 | ZAPATA DE 15 X 60 CM Y CONTRATRABE DE 15 X 85 CM, (D-431-01-4-4854) | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.242000 | $1,568.24 | $379.51 |
| CONC. F-C=100KG/CM2. | CONCRETO HECHO EN OBRA F'C=100 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 | 0.047300 | $950.72 | $44.97 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.289300 | $134.17 | $38.82 |
| CIMBRA COMUN CIMENTA | CIMBRA COMUN DE MADERA DE PINO DE 2da. | M2 | 2.200000 | $151.18 | $332.60 |
| ACERO CIMEN. NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.016690 | $9,192.72 | $153.43 |
| ACERO CIMEN. NO. 5 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 5 ( 5/8" ) DE DIAM. | TON | 0.006860 | $8,564.97 | $58.76 |
| EXCAVACION | EXCAVACION CON EQUIPO PESADO | M3 | 0.924000 | $36.03 | $33.29 |
| Suma de Auxiliar | $1,041.37 | ||||
| Costo Directo | $1,041.37 |