| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 95 | DE 15 X 30 CM (D-431-01-4-4600) | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.049500 | $1,568.24 | $77.63 |
| CONC. F-C=100KG/CM2. | CONCRETO HECHO EN OBRA F'C=100 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 | 0.012500 | $950.72 | $11.88 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.062000 | $134.17 | $8.32 |
| ACERO CIMEN. NO. 2 | HABILITADO Y ARMADO DE ACERO DE REFUERZO F'Y = 2530 KG/CM2, DEL #2 (1/4") EN CIMENTACIÓN. | TON | 0.001380 | $8,944.41 | $12.34 |
| ACERO CIMEN. NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.003080 | $9,192.72 | $28.31 |
| CIMBRA COMUN CIMENTA | CIMBRA COMUN DE MADERA DE PINO DE 2da. | M2 | 0.300000 | $151.18 | $45.35 |
| EXCAVACION | EXCAVACION CON EQUIPO PESADO | M3 | 0.049500 | $36.03 | $1.78 |
| Suma de Auxiliar | $185.62 | ||||
| Costo Directo | $185.62 |