| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 189 | CON PERFILES SEMIPESADOS DE 12 A 60 KG/ML, (D-431.01-4-4839, 4863, 4600, 4150, 4775, 4635, 4852, 4200, 4275, 4280, 4285, 4290, 4295) | ton |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PERFILES SEMIPESADOS | PERFILES SEMIPESADOS DE ACERO AL CARBON DE 12 A 60 KG/ML | ton | 1.100000 | $8,156.98 | $8,972.68 |
| MAT-CON004 | SOLDADURA NOM H-77 AWS E-6010, 7018 | KG | 30.000000 | $19.18 | $575.40 |
| CON007 | CARDA CIRCULAR TRENZADA | PZA | 2.000000 | $239.82 | $479.64 |
| MAT-CON001 | OXIGENO | M3 | 10.000000 | $37.41 | $374.10 |
| MAT-CON002 | ACETILENO | KG | 5.000000 | $133.34 | $666.70 |
| PIN001 | PRIMARIO INORGANICO DE ZINC RP-4 TIPO "B" | LT | 10.000000 | $121.57 | $1,215.70 |
| CON-005A | ARENA SILICA MALLA 16/30 (TON) | TON | 2.500000 | $741.54 | $1,853.85 |
| PIN012 | ACABADO RA-26 | LT | 12.000000 | $143.89 | $1,726.68 |
| MA-307 | THINNER | LT | 6.000000 | $11.96 | $71.76 |
| Suma de Material | $15,936.51 | ||||
| Mano de Obra | |||||
| CUAD014 | CUADRILLA OPERARIO ESPECIALISTA SOLDADOR + AYUDANTE | jor | 2.250000 | $832.18 | $1,872.41 |
| CUAD036 | CUADRILLA OPERARIO ESPECIALISTA PAILERO + AYUDANTE | jor | 2.250000 | $832.18 | $1,872.41 |
| CUAD017 | CUADRILLA SAND BLASTERO-PINTOR + AYUDANTE | jor | 2.250000 | $832.18 | $1,872.41 |
| Suma de Mano de Obra | $5,617.22 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MAQ031 | EQUIPO PARA SOLDURA Y CORTE | hora | 22.500000 | $62.95 | $1,416.38 |
| MAQ012 | EQUIPO PARA SAND BLAST Y PINTURA | hora | 22.500000 | $141.60 | $3,186.00 |
| MAQ411 | EQUIPO GRUA AUTOPROPULSADA | hora | 0.200000 | $309.43 | $61.89 |
| Suma de Equipo | $4,664.26 | ||||
| Costo Directo | $26,217.98 |