| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 24 | CISTERNA DE 180 x 280 x 285 CM, (D-431-01-4-4745, 4760) | Pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| LI11/2X1/4 | ANGULO LI DE ACERO AL CARBON DE 1 1/2" X 1/4" ASTM-A-36 | KG | 37.900000 | $8.16 | $309.26 |
| LI11/4X1/4 | ANGULO LI DE ACERO AL CARBON DE 1 1/4" X 1/4" ASTM-A-36 | KG | 31.145400 | $8.16 | $254.15 |
| REDONDO LISO #3 | ANCLA DE ACERO REDONDO LISO # 3 | KG | 4.880000 | $8.16 | $39.82 |
| REDONDO LISO #5 | ACERO REDONDO LISO # 5 | KG | 16.400000 | $8.16 | $133.82 |
| TUBO ALUM. 76 MM | TUBO CONDUIT DE ALUMINIO LIBRE DE COBRE, PARED GRUESA, CUERDA ESTANDAR EN LOS EXTREMOS Y COPLES, DE 76 MM DE DIAM. | MTS | 0.900000 | $599.76 | $539.78 |
| CODO 90 X 76 MM | CODO GALVANIZADO DE 90 GRADOS, 76 MM | PZA | 2.000000 | $59.32 | $118.64 |
| MAT-CON004 | SOLDADURA NOM H-77 AWS E-6010, 7018 | KG | 2.697600 | $19.18 | $51.74 |
| CON-005A | ARENA SILICA MALLA 16/30 (TON) | TON | 0.224800 | $741.54 | $166.70 |
| PIN001 | PRIMARIO INORGANICO DE ZINC RP-4 TIPO "B" | LT | 0.899200 | $121.57 | $109.32 |
| PIN012 | ACABADO RA-26 | LT | 1.079040 | $143.89 | $155.26 |
| MA-307 | THINNER | LT | 0.539520 | $11.96 | $6.45 |
| MAT-CON001 | OXIGENO | M3 | 0.899200 | $37.41 | $33.64 |
| MAT-CON002 | ACETILENO | KG | 0.449600 | $133.34 | $59.95 |
| MAT-CON003 | DISCO ABRASIVO DE 1/4" | PZA | 0.200000 | $57.55 | $11.51 |
| Suma de Material | $1,990.05 | ||||
| Mano de Obra | |||||
| CUAD014 | CUADRILLA OPERARIO ESPECIALISTA SOLDADOR + AYUDANTE | jor | 0.224800 | $832.18 | $187.07 |
| CUAD036 | CUADRILLA OPERARIO ESPECIALISTA PAILERO + AYUDANTE | jor | 0.224800 | $832.18 | $187.07 |
| CUAD016 | CUADRILLA OPERARIO ESPECIALISTA PINTOR + AYUDANTE | jor | 0.224800 | $819.83 | $184.30 |
| Suma de Mano de Obra | $558.45 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MAQ031 | EQUIPO PARA SOLDURA Y CORTE | hora | 2.248000 | $62.95 | $141.51 |
| MAQ053 | EQUIPO PARA PINTURA | hora | 2.248000 | $135.43 | $304.45 |
| Suma de Equipo | $445.96 | ||||
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 4.912260 | $1,568.24 | $7,703.60 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 5.149860 | $134.17 | $690.96 |
| CONC. F-C=100KG/CM2. | CONCRETO HECHO EN OBRA F'C=100 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 | 0.237600 | $950.72 | $225.89 |
| ACERO REFZO NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.368500 | $9,192.72 | $3,387.52 |
| EXCAVACION | EXCAVACION CON EQUIPO PESADO | M3 | 14.364000 | $36.03 | $517.53 |
| CIMBRA COMUN CIMENTA | CIMBRA COMUN DE MADERA DE PINO DE 2da. | M2 | 26.220000 | $151.18 | $3,963.94 |
| ACABADO | ACABADO PULIDO INTEGRAL A PLANA METALICA SOBRE FIRME DE CONCRETO CON POLVOREADO CON CEMENTO GRIS | M2 | 35.300000 | $35.22 | $1,243.27 |
| Suma de Auxiliar | $17,732.71 | ||||
| Costo Directo | $20,727.16 |