| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 191 | SUMINISTRO Y COLOCACION DE ESCALONES DE FIERRO COLADO, EMPOTRADOS EN MURO DE CONCRETO, PARA ESCALERA MARINA, (D-431.01-4-4550) | pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CON007 | CARDA CIRCULAR TRENZADA | PZA | 2.000000 | $239.82 | $479.64 |
| PIN001 | PRIMARIO INORGANICO DE ZINC RP-4 TIPO "B" | LT | 10.000000 | $121.57 | $1,215.70 |
| CON-005A | ARENA SILICA MALLA 16/30 (TON) | TON | 2.500000 | $741.54 | $1,853.85 |
| PIN012 | ACABADO RA-26 | LT | 12.000000 | $143.89 | $1,726.68 |
| MA-307 | THINNER | LT | 6.000000 | $11.96 | $71.76 |
| SOLERA 1/4"X11/2" | SOLERA DE ACERO AL CARBON DE 1/4" X 1 1/2" | kg | 4.340000 | $8.16 | $35.41 |
| REDONDO DE 1/2" | REDONDO DE ACERO AL CARBON DE 1/2" | kg | 10.450000 | $8.16 | $85.27 |
| MAT-CON004 | SOLDADURA NOM H-77 AWS E-6010, 7018 | KG | 0.250000 | $19.18 | $4.80 |
| MAT-CON003 | DISCO ABRASIVO DE 1/4" | PZA | 0.020000 | $57.55 | $1.15 |
| MAT-CON001 | OXIGENO | M3 | 0.040000 | $37.41 | $1.50 |
| MAT-CON002 | ACETILENO | KG | 0.020000 | $133.34 | $2.67 |
| Suma de Material | $5,478.43 | ||||
| Mano de Obra | |||||
| CUAD014 | CUADRILLA OPERARIO ESPECIALISTA SOLDADOR + AYUDANTE | jor | 2.000000 | $832.18 | $1,664.36 |
| CUAD036 | CUADRILLA OPERARIO ESPECIALISTA PAILERO + AYUDANTE | jor | 2.000000 | $832.18 | $1,664.36 |
| CUAD017 | CUADRILLA SAND BLASTERO-PINTOR + AYUDANTE | jor | 2.000000 | $832.18 | $1,664.36 |
| CUAD038 | CUADRILLA OPERARIO ESPECIALISTA HERRERO + AYUDANTE | jor | 0.125000 | $795.15 | $99.39 |
| Suma de Mano de Obra | $5,092.47 | ||||
| Herramienta | |||||
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MAQ411 | EQUIPO GRUA AUTOPROPULSADA | hora | 0.020000 | $309.43 | $6.19 |
| Suma de Equipo | $6.19 | ||||
| Auxiliar | |||||
| CONC. F-C=200KG/CM2. | CONCRETO HECHO EN OBRA F'C=200 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.020000 | $1,453.67 | $29.07 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.020000 | $134.17 | $2.68 |
| AUX003 | TRATAMIENTO ANTICORROSIVO A BASE DE LIMPIEZA CON CHORRO DE ARENA LA-80, APLICACION DE PRIMARIO ESP. PEMEX RP-4, ACABADO EPOXI-POLIAMIDA DE ALTOS SOLIDOS ESP. PEMEX RA-26-80 | M2 | 0.765086 | $258.23 | $197.57 |
| Suma de Auxiliar | $229.32 | ||||
| Costo Directo | $10,806.41 |