| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 195 | SUMINISTRO Y FABRICACIÓN DE TAPA A BASE DE CONCRETO ARMADO, CON MARCO Y CONTRAMARCO DE ANGULOS, INCLUYE: SUMINISTRO, MATERIALES, COLOCACIÓN, HERRAMIENTAS Y MANO DE OBRA, (D-431.01-4-4550) | m² |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| LI11/4X1/4 | ANGULO LI DE ACERO AL CARBON DE 1 1/4" X 1/4" ASTM-A-36 | KG | 9.249240 | $8.16 | $75.47 |
| LI11/2X1/4 | ANGULO LI DE ACERO AL CARBON DE 1 1/2" X 1/4" ASTM-A-36 | KG | 11.484000 | $8.16 | $93.71 |
| MAT-CON004 | SOLDADURA NOM H-77 AWS E-6010, 7018 | KG | 0.350000 | $19.18 | $6.71 |
| CON-005A | ARENA SILICA MALLA 16/30 (TON) | TON | 0.050000 | $741.54 | $37.08 |
| PIN001 | PRIMARIO INORGANICO DE ZINC RP-4 TIPO "B" | LT | 0.150000 | $121.57 | $18.24 |
| PIN012 | ACABADO RA-26 | LT | 0.150000 | $143.89 | $21.58 |
| MA-307 | THINNER | LT | 0.080000 | $11.96 | $0.96 |
| MAT-CON001 | OXIGENO | M3 | 0.200000 | $37.41 | $7.48 |
| MAT-CON002 | ACETILENO | KG | 0.100000 | $133.34 | $13.33 |
| MAT-CON003 | DISCO ABRASIVO DE 1/4" | PZA | 0.020000 | $57.55 | $1.15 |
| Suma de Material | $275.72 | ||||
| Mano de Obra | |||||
| CUAD038 | CUADRILLA OPERARIO ESPECIALISTA HERRERO + AYUDANTE | jor | 0.333330 | $795.15 | $265.05 |
| CUAD016 | CUADRILLA OPERARIO ESPECIALISTA PINTOR + AYUDANTE | jor | 0.100000 | $819.83 | $81.98 |
| Suma de Mano de Obra | $347.03 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MAQ031 | EQUIPO PARA SOLDURA Y CORTE | hora | 3.333300 | $62.95 | $209.83 |
| MAQ053 | EQUIPO PARA PINTURA | hora | 10.000000 | $135.43 | $1,354.30 |
| Suma de Equipo | $1,564.13 | ||||
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.088000 | $1,568.24 | $138.01 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.088000 | $134.17 | $11.81 |
| CIMBRA COMUN LOSAS | CIMBRA COMUN EN MUROS, COLUMNAS, TRABES Y LOSAS. | M2 | 1.100000 | $176.10 | $193.71 |
| ACERO ESTRUC. NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.008211 | $9,398.41 | $77.17 |
| ACERO ESTRUC. NO. 2 | HABILITADO Y ARMADO DE ACERO DE REFUERZO F'Y = 2530 KG/CM2, DEL #2 (1/4") | TON | 0.005326 | $8,944.41 | $47.64 |
| Suma de Auxiliar | $468.33 | ||||
| Costo Directo | $2,655.21 |