| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 169 | DE 15 CM DE ESPESOR, (D-431.01-4-4310, 4857) | m² |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.165000 | $1,568.24 | $258.76 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.165000 | $134.17 | $22.14 |
| CIMBRA COMUN LOSAS | CIMBRA COMUN EN MUROS, COLUMNAS, TRABES Y LOSAS. | M2 | 1.100000 | $176.10 | $193.71 |
| ACERO ESTRUC. NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.011700 | $9,398.41 | $109.96 |
| Suma de Auxiliar | $584.57 | ||||
| Costo Directo | $584.57 |