| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 530 | 24” DIAM. (609 MM) LIMPIEZA | METROS |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CON-005A | ARENA SILICA MALLA 16/30 (TON) | TON | 0.095760 | $741.54 | $71.01 |
| PIN001 | PRIMARIO INORGANICO DE ZINC RP-4 TIPO "B" | LT | 0.233550 | $121.57 | $28.39 |
| PIN012 | ACABADO RA-26 | LT | 0.797970 | $143.89 | $114.82 |
| PIN006 | SOLVENTE 50/50 | LT | 0.011680 | $8.14 | $0.10 |
| PIN007 | SOLVENTE 80/20 | LT | 0.159590 | $11.29 | $1.80 |
| CON-006 | TRAPO DE ALGODON | KG | 0.038300 | $46.27 | $1.77 |
| MA-307 | THINNER | LT | 0.191510 | $11.96 | $2.29 |
| Suma de Material | $220.18 | ||||
| Mano de Obra | |||||
| CUAD017 | CUADRILLA SAND BLASTERO-PINTOR + AYUDANTE | jor | 0.112650 | $832.18 | $93.75 |
| Suma de Mano de Obra | $93.75 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MAQ012 | EQUIPO PARA SAND BLAST Y PINTURA | hora | 1.126500 | $141.60 | $159.51 |
| Suma de Equipo | $159.51 | ||||
| Costo Directo | $473.44 |