| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 525 | 8” DIAM. (203 MM) LIMPIEZA | METROS |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CON-005A | ARENA SILICA MALLA 16/30 (TON) | TON | 0.034430 | $741.54 | $25.53 |
| PIN001 | PRIMARIO INORGANICO DE ZINC RP-4 TIPO "B" | LT | 0.083980 | $121.57 | $10.21 |
| PIN012 | ACABADO RA-26 | LT | 0.286930 | $143.89 | $41.29 |
| PIN006 | SOLVENTE 50/50 | LT | 0.004200 | $8.14 | $0.03 |
| PIN007 | SOLVENTE 80/20 | LT | 0.057390 | $11.29 | $0.65 |
| CON-006 | TRAPO DE ALGODON | KG | 0.013770 | $46.27 | $0.64 |
| MA-307 | THINNER | LT | 0.068860 | $11.96 | $0.82 |
| Suma de Material | $79.17 | ||||
| Mano de Obra | |||||
| CUAD017 | CUADRILLA SAND BLASTERO-PINTOR + AYUDANTE | jor | 0.040510 | $832.18 | $33.71 |
| Suma de Mano de Obra | $33.71 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MAQ012 | EQUIPO PARA SAND BLAST Y PINTURA | hora | 0.405100 | $141.60 | $57.36 |
| Suma de Equipo | $57.36 | ||||
| Costo Directo | $170.24 |