| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 921 | REACONDICIONAMIENTO DE TANQUE EXISTENTE PARA AGUA POTABLE (FB-101) CON CABEZAS SEMIELIPTICAS, DE DIAMETRO EXTERIOR DE 3700 MM Y DISTANCIA ENTRE LINEAS DE TANGENCIAS DE 4270 MM, CAPACIDAD DE 42.043 M3 , DE ACUERDO CON LO ESPECIFICADO EN EL API 650, ANEXO B1 Y PLANO DE REFERENCIA: D-431-01-8-8200 INCLUYE: PRUEBAS ESPECIFICADAS EN EL API 650, CARGA DESCARGA Y ACARREO DE MATERIALES, NIVELACIÓN, FIJACION DEL EQUIPO EN SU RESPECTIVO SOPORTE, SUMINISTRO DE REFACCIONAMIENTO PARA PRUEBA Y PUESTA EN OPERACIÓN, APLICACIÓN EN EL SITIO DE RECUBRIMIENTO PRIMARIO Y ACABADO FINAL EN EL EXTERIOR DEL TANQUE DE ALMACENAMIENTO CONFORME A LAS ESPECIFICACIONES DE PEMEX P.2.411.01, P.3.411.01 Y P.4.411.01. | EQUIPO |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PL5/16 | PLACA DE ACERO AL CARBON DE 5/16" DE ESPESOR ASTM-A-36 | KG | 1,222.270000 | $8.16 | $9,973.72 |
| TUB184 | TUBERIA OC-60 X 3.91 CED. 40 | MTS | 58.363000 | $104.46 | $6,096.60 |
| LI2X1/4 | ANGULO LI DE ACERO AL CARBON DE 2" X 1/4" ASTM-A-36 | KG | 407.270000 | $8.16 | $3,323.32 |
| IR15 | VIGA IR-152 X 24 DE ACERO AL CARBON ASTM-A-36 | ML | 20.000000 | $195.77 | $3,915.40 |
| IR203 | VIGA IR-203 X 26.6 DE ACERO AL CARBON ASTM-A-36 | ML | 38.000000 | $216.98 | $8,245.24 |
| MAT-CON004 | SOLDADURA NOM H-77 AWS E-6010, 7018 | KG | 90.000000 | $19.18 | $1,726.20 |
| MAT-CON003 | DISCO ABRASIVO DE 1/4" | PZA | 20.000000 | $57.55 | $1,151.00 |
| MAT-CON001 | OXIGENO | M3 | 125.000000 | $37.41 | $4,676.25 |
| MAT-CON002 | ACETILENO | KG | 60.000000 | $133.34 | $8,000.40 |
| CON-005A | ARENA SILICA MALLA 16/30 (TON) | TON | 0.050000 | $741.54 | $37.08 |
| PIN001 | PRIMARIO INORGANICO DE ZINC RP-4 TIPO "B" | LT | 0.280000 | $121.57 | $34.04 |
| PIN003 | ACABADO DE POLIURETANO RA-28 | LT | 0.270000 | $87.31 | $23.57 |
| PIN012 | ACABADO RA-26 | LT | 0.370000 | $143.89 | $53.24 |
| PIN006 | SOLVENTE 50/50 | LT | 0.060000 | $8.14 | $0.49 |
| PIN007 | SOLVENTE 80/20 | LT | 0.090000 | $11.29 | $1.02 |
| PIN010 | SOLVENTE 40/41/19 | LT | 0.050000 | $25.63 | $1.28 |
| MA-307 | THINNER | LT | 0.120000 | $11.96 | $1.44 |
| CON007 | CARDA CIRCULAR TRENZADA | PZA | 4.000000 | $239.82 | $959.28 |
| Suma de Material | $48,219.57 | ||||
| Mano de Obra | |||||
| CUAD023 | CUADRILLA PARA TANQUES = (2) SOLDADOR + (2) PAILERO + (1) SAND BLASTERO PINTOR + (5) AYUDANTES DE OPERARIOS + (2 MANIOBRISTAS + (2) OBREROS GENERALES | jor | 30.303030 | $5,845.48 | $177,135.76 |
| Suma de Mano de Obra | $177,135.76 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MAQ032 | EQUIPO PARA SOLDADOR + PAILERIA + ANDAMIOS + CARGA | hora | 303.030300 | $336.98 | $102,115.15 |
| Suma de Equipo | $102,115.15 | ||||
| Costo Directo | $327,470.47 |