| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 13 | SECCIÓN DE CONCRETO DE 45 x 45 cm PARA TUBERÍA DE 20 cm DE DIÁMETRO. (D-431-01-4-4045) | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONC. F-C=100KG/CM2. | CONCRETO HECHO EN OBRA F'C=100 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 | 0.025000 | $950.72 | $23.77 |
| CONC. F-C=200KG/CM2. | CONCRETO HECHO EN OBRA F'C=200 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.191334 | $1,453.67 | $278.14 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.216334 | $134.17 | $29.03 |
| CIMBRA COMUN CIMENTA | CIMBRA COMUN DE MADERA DE PINO DE 2da. | M2 | 1.210000 | $151.18 | $182.93 |
| ACERO CIMEN. NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.003900 | $9,192.72 | $35.85 |
| ACERO CIMEN. NO. 6 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 6 ( 3/4" ) DE DIAM. | TON | 0.014850 | $8,410.57 | $124.90 |
| EXCAVACION | EXCAVACION CON EQUIPO PESADO | M3 | 0.675000 | $36.03 | $24.32 |
| Suma de Auxiliar | $698.93 | ||||
| Costo Directo | $698.93 |