| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 175 | DE 15 CM. DE ESPESOR, (D-431.01-4-4830, 4825, 4835, 4821, 4844, 4837, 4840, 4861, 4600, 4430, 4305, 4445, 4630, 4850, 4195, 4846) | m² |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| M6X6-4/4 | MALLA ELECTROSOLDADA 6x6-4/4, ESTIRADA EN FRIO fy= 5000 kg/cm². MARCA HILSA. | m2 | 1.100000 | $44.25 | $48.68 |
| Suma de Material | $48.68 | ||||
| Mano de Obra | |||||
| CUAD010 | CUADRILLA FIERRERO + AYUDANTE | jor | 0.100000 | $795.15 | $79.52 |
| Suma de Mano de Obra | $79.52 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.150000 | $1,568.24 | $235.24 |
| CONC. F-C=100KG/CM2. | CONCRETO HECHO EN OBRA F'C=100 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 | 0.050000 | $950.72 | $47.54 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.200000 | $134.17 | $26.83 |
| Suma de Auxiliar | $309.61 | ||||
| Costo Directo | $437.80 |