| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 23 | CISTERNA DE 230 x 330 x 240 CM, (D-431-01-4-4750) | Pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| LI11/2X1/4 | ANGULO LI DE ACERO AL CARBON DE 1 1/2" X 1/4" ASTM-A-36 | KG | 37.900000 | $8.16 | $309.26 |
| LI11/4X1/4 | ANGULO LI DE ACERO AL CARBON DE 1 1/4" X 1/4" ASTM-A-36 | KG | 31.145400 | $8.16 | $254.15 |
| REDONDO LISO #3 | ANCLA DE ACERO REDONDO LISO # 3 | KG | 4.880000 | $8.16 | $39.82 |
| REDONDO LISO #5 | ACERO REDONDO LISO # 5 | KG | 16.400000 | $8.16 | $133.82 |
| MAT-CON004 | SOLDADURA NOM H-77 AWS E-6010, 7018 | KG | 2.671200 | $19.18 | $51.23 |
| CON-005A | ARENA SILICA MALLA 16/30 (TON) | TON | 0.222600 | $741.54 | $165.07 |
| PIN001 | PRIMARIO INORGANICO DE ZINC RP-4 TIPO "B" | LT | 0.890400 | $121.57 | $108.25 |
| PIN012 | ACABADO RA-26 | LT | 1.068480 | $143.89 | $153.74 |
| MA-307 | THINNER | LT | 0.534240 | $11.96 | $6.39 |
| MAT-CON001 | OXIGENO | M3 | 0.890400 | $37.41 | $33.31 |
| MAT-CON002 | ACETILENO | KG | 0.445200 | $133.34 | $59.36 |
| MAT-CON003 | DISCO ABRASIVO DE 1/4" | PZA | 0.200000 | $57.55 | $11.51 |
| Suma de Material | $1,325.92 | ||||
| Mano de Obra | |||||
| CUAD014 | CUADRILLA OPERARIO ESPECIALISTA SOLDADOR + AYUDANTE | jor | 0.222600 | $832.18 | $185.24 |
| CUAD036 | CUADRILLA OPERARIO ESPECIALISTA PAILERO + AYUDANTE | jor | 0.222600 | $832.18 | $185.24 |
| CUAD016 | CUADRILLA OPERARIO ESPECIALISTA PINTOR + AYUDANTE | jor | 0.222600 | $819.83 | $182.49 |
| Suma de Mano de Obra | $552.98 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MAQ031 | EQUIPO PARA SOLDURA Y CORTE | hora | 2.226000 | $62.95 | $140.13 |
| MAQ053 | EQUIPO PARA PINTURA | hora | 2.226000 | $135.43 | $301.47 |
| Suma de Equipo | $441.59 | ||||
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 6.251000 | $1,568.24 | $9,803.07 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 7.041000 | $134.17 | $944.69 |
| CONC. F-C=100KG/CM2. | CONCRETO HECHO EN OBRA F'C=100 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 | 0.790000 | $950.72 | $751.07 |
| ACERO REFZO NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.468970 | $9,192.72 | $4,311.11 |
| EXCAVACION | EXCAVACION CON EQUIPO PESADO | M3 | 18.216000 | $36.03 | $656.32 |
| ACERO REFZO NO. 4 | HABILITADO Y ARMADO DE ACERO DE REFUERZO FY=4200 KG/CM2. DEL No. 4 ( 1/2" ) DE DIAM. | TON | 0.007700 | $9,192.72 | $70.78 |
| CIMBRA COMUN CIMENTA | CIMBRA COMUN DE MADERA DE PINO DE 2da. | M2 | 29.600000 | $151.18 | $4,474.93 |
| ACABADO | ACABADO PULIDO INTEGRAL A PLANA METALICA SOBRE FIRME DE CONCRETO CON POLVOREADO CON CEMENTO GRIS | M2 | 41.060000 | $35.22 | $1,446.13 |
| Suma de Auxiliar | $22,458.11 | ||||
| Costo Directo | $24,778.60 |