| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 117 | ZAPATA DE 30 X 100 CM Y CONTRATRABE DE 30 X 70 CM, (D-431-01-4-4240, 4255) | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.462000 | $1,568.24 | $724.53 |
| CONC. F-C=100KG/CM2. | CONCRETO HECHO EN OBRA F'C=100 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 | 0.066000 | $950.72 | $62.75 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.528000 | $134.17 | $70.84 |
| CIMBRA COMUN CIMENTA | CIMBRA COMUN DE MADERA DE PINO DE 2da. | M2 | 1.540000 | $151.18 | $232.82 |
| ACERO CIMEN. NO. 4 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 4 ( 1/2" ) DE DIAM. | TON | 0.041580 | $8,944.41 | $371.91 |
| ACERO CIMEN. NO. 6 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 6 ( 3/4" ) DE DIAM. | TON | 0.014850 | $8,410.57 | $124.90 |
| EXCAVACION | EXCAVACION CON EQUIPO PESADO | M3 | 1.452000 | $36.03 | $52.32 |
| Suma de Auxiliar | $1,640.05 | ||||
| Costo Directo | $1,640.05 |