| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3 | RELLENO COMPACTADO AL 95% PROCTOR EN CAPAS DE 20 cm CON MATERIAL DE BANCO Y CEMENTADO EN PROPORCION DE 80 kg DE CEMENTO POR m3 PARA FORMACION DE TERRAPLENES (PLATAFORMA GENERAL). INCLUYE : SUMINISTRO DEL MATERIAL, CARGA ACARREO EN EL 1er km Y kms SUBSECUENTES, (E-431-01-4-4005) | m³ |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONS006 | CEMENTO GRIS PORTLAND | TON | 0.080000 | $1,671.17 | $133.69 |
| ARERELL | ARENA PARA RELLENO | M3 | 1.150000 | $124.47 | $143.14 |
| CONS001 | AGUA PUESTA EN OBRA EN PIPA | M3 | 0.300000 | $19.77 | $5.93 |
| Suma de Material | $282.77 | ||||
| Mano de Obra | |||||
| CUAD047 | CUADRILLA AYUDANTES GENERALES | jor | 0.025000 | $536.33 | $13.41 |
| Suma de Mano de Obra | $13.41 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MAQ433 | EQUIPO PARA MEJORAMIENTO DE RELLENO | hora | 0.012500 | $512.53 | $6.41 |
| Suma de Equipo | $6.41 | ||||
| Costo Directo | $302.58 |