| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 170 | DE 20 CM DE ESPESOR, (D-431.01-4-4861) | m² |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.220000 | $1,568.24 | $345.01 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.220000 | $134.17 | $29.52 |
| CIMBRA COMUN LOSAS | CIMBRA COMUN EN MUROS, COLUMNAS, TRABES Y LOSAS. | M2 | 1.100000 | $176.10 | $193.71 |
| ACERO ESTRUC. NO. 4 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA FY=4200 KG/CM2. DEL No. 4 ( 1/2" ) DE DIAM. | TON | 0.022000 | $9,131.61 | $200.90 |
| Suma de Auxiliar | $769.14 | ||||
| Costo Directo | $769.14 |