| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 576 | 24” DIAM (610 MM) 150 # R.F. | PIEZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CON-005A | ARENA SILICA MALLA 16/30 (TON) | TON | 0.030540 | $741.54 | $22.65 |
| PIN001 | PRIMARIO INORGANICO DE ZINC RP-4 TIPO "B" | LT | 0.074490 | $121.57 | $9.06 |
| PIN006 | SOLVENTE 50/50 | LT | 0.003720 | $8.14 | $0.03 |
| PIN012 | ACABADO RA-26 | LT | 0.254500 | $143.89 | $36.62 |
| PIN007 | SOLVENTE 80/20 | LT | 0.050900 | $11.29 | $0.57 |
| CON-006 | TRAPO DE ALGODON | KG | 0.012220 | $46.27 | $0.57 |
| MA-307 | THINNER | LT | 0.061080 | $11.96 | $0.73 |
| Suma de Material | $70.22 | ||||
| Mano de Obra | |||||
| CUAD017 | CUADRILLA SAND BLASTERO-PINTOR + AYUDANTE | jor | 0.035930 | $832.18 | $29.90 |
| Suma de Mano de Obra | $29.90 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MAQ012 | EQUIPO PARA SAND BLAST Y PINTURA | hora | 0.359300 | $141.60 | $50.88 |
| Suma de Equipo | $50.88 | ||||
| Costo Directo | $151.00 |