| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 86 | ZAPATAS DE 220 X 325 CM Y 25 CM DE ALTURA, CON DADO DE 60 X 60 CM (D-431-01-4-4270) | Pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 2.559700 | $1,568.24 | $4,014.22 |
| CONC. F-C=100KG/CM2. | CONCRETO HECHO EN OBRA F'C=100 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 | 0.423500 | $950.72 | $402.63 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 2.983200 | $134.17 | $400.26 |
| ACERO CIMEN. NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.068468 | $9,192.72 | $629.41 |
| ACERO CIMEN. NO. 4 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 4 ( 1/2" ) DE DIAM. | TON | 0.106865 | $8,944.41 | $955.84 |
| ACERO CIMEN. NO. 6 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 6 ( 3/4" ) DE DIAM. | TON | 0.037620 | $8,410.57 | $316.41 |
| CIMBRA COMUN CIMENTA | CIMBRA COMUN DE MADERA DE PINO DE 2da. | M2 | 6.957500 | $151.18 | $1,051.83 |
| EXCAVACION | EXCAVACION CON EQUIPO PESADO | M3 | 10.170600 | $36.03 | $366.45 |
| Suma de Auxiliar | $8,137.05 | ||||
| Costo Directo | $8,137.05 |