| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 36 | SECCIÓN DE 25 X 40 CM CON 2 TUBOS DE ø 76 MM | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CR | COLORANTE ROJO 7.5 kg/m3 | kg | 0.825000 | $57.55 | $47.48 |
| TUBO ALUM. 76 MM | TUBO CONDUIT DE ALUMINIO LIBRE DE COBRE, PARED GRUESA, CUERDA ESTANDAR EN LOS EXTREMOS Y COPLES, DE 76 MM DE DIAM. | MTS | 2.200000 | $599.76 | $1,319.47 |
| M6X6-10/10 | MALLA ELECTROSOLDADA 6x6-10/10, ESTIRADA EN FRIO fy= 5000 kg/cm². MARCA HILSA. | m2 | 1.430000 | $43.01 | $61.50 |
| Suma de Material | $1,428.46 | ||||
| Mano de Obra | |||||
| CUAD047 | CUADRILLA AYUDANTES GENERALES | jor | 0.264000 | $536.33 | $141.59 |
| CUAD001 | CUADRILLA ELECTRICO + AYUDANTE | jor | 0.120000 | $819.83 | $98.38 |
| Suma de Mano de Obra | $239.97 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MAQ042 | EQUIPO TARRAJA | hora | 1.000000 | $3.39 | $3.39 |
| Suma de Equipo | $3.39 | ||||
| Auxiliar | |||||
| CONC. F-C=100KG/CM2. | CONCRETO HECHO EN OBRA F'C=100 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 | 0.027500 | $950.72 | $26.14 |
| CONC. F-C=175KG/CM2. | CONCRETO HECHO EN OBRA F'C=175 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.100927 | $1,458.91 | $147.24 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.128427 | $134.17 | $17.23 |
| EXCAVACION | EXCAVACION CON EQUIPO PESADO | M3 | 0.480000 | $36.03 | $17.29 |
| ACERO CIMEN. NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.002460 | $9,192.72 | $22.61 |
| ACERO CIMEN. NO. 4 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 4 ( 1/2" ) DE DIAM. | TON | 0.007150 | $8,944.41 | $63.95 |
| CIMBRA COMUN CIMENTA | CIMBRA COMUN DE MADERA DE PINO DE 2da. | M2 | 0.500000 | $151.18 | $75.59 |
| Suma de Auxiliar | $370.07 | ||||
| Costo Directo | $2,041.89 |