| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 162 | DE 15 X 45 CM, (D-431.01-4-4610) | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.074250 | $1,568.24 | $116.44 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.074250 | $134.17 | $9.96 |
| CIMBRA APARENTE TRAB | CIMBRA APARENTE EN MUROS, COLUMNAS, TRABES Y LOSAS. | M2 | 1.540000 | $215.94 | $332.55 |
| ACERO ESTRUC. NO. 2 | HABILITADO Y ARMADO DE ACERO DE REFUERZO F'Y = 2530 KG/CM2, DEL #2 (1/4") | TON | 0.002761 | $8,944.41 | $24.70 |
| ACERO ESTRUC. NO. 4 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA FY=4200 KG/CM2. DEL No. 4 ( 1/2" ) DE DIAM. | TON | 0.006600 | $9,131.61 | $60.27 |
| Suma de Auxiliar | $543.92 | ||||
| Costo Directo | $543.92 |