| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 104 | ZAPATA DE 25 X 400, MURO DE 25 CM DE ESPESOR Y ALTURA VARIABLE, (D-431-01-4-4296, 4297) | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 2.464000 | $1,568.24 | $3,864.14 |
| CONC. F-C=100KG/CM2. | CONCRETO HECHO EN OBRA F'C=100 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 | 0.231000 | $950.72 | $219.62 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 2.695000 | $134.17 | $361.59 |
| CIMBRA COMUN CIMENTA | CIMBRA COMUN DE MADERA DE PINO DE 2da. | M2 | 11.462000 | $151.18 | $1,732.83 |
| ACERO CIMEN. NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.027104 | $9,192.72 | $249.16 |
| ACERO CIMEN. NO. 4 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 4 ( 1/2" ) DE DIAM. | TON | 0.043648 | $8,944.41 | $390.41 |
| ACERO CIMEN. NO. 5 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 5 ( 5/8" ) DE DIAM. | TON | 0.154577 | $8,564.97 | $1,323.95 |
| EXCAVACION | EXCAVACION CON EQUIPO PESADO | M3 | 5.412000 | $36.03 | $194.99 |
| Suma de Auxiliar | $8,336.68 | ||||
| Costo Directo | $8,336.68 |